Project Update 11/09/17

DK Contactors’ sewer crew has completed the storm sewer installation for the Keystone/Chartres Project on Friday November 3rd. Current operations have switched to completing final restoration for this project. Crews began general cleanup of the site and prepped areas for pavement restoration. Concrete paving for curb & gutter and sidewalk will be completed by the end of this week with asphalt paving to take place on Monday and Tuesday November 13th & 14th. Following pavement restoration, the final restoration of grass, shrubs and trees will take place.

Please check back weekly for project updates.