Project Update 10/07/17

The contractor has completed final grading in West Park. A new asphalt path has been installed and landscapers are beginning to seed and plant trees.

Next week the landscapers will finish their work in West Park and the sewer crew will return to begin placing new sewer on Koepke Road proceeding north towards Keystone Road.

There will be periodic closures on Koepke Road beginning next week.  Signs alerting motorists to closures and detours will be posted.

Please check back weekly for project updates.

West Park grading