Project Update 09/21/17

This week DK Contractors began their underground work in West Park. This included lowering a water main along the south side of the park as well as the installation of storm sewer, inlets and catch basins throughout the park.

Beginning early next week, the new storm sewer placement will proceed from West Park north across Koepke Road. This will result in short term road closures on Koepke Road. Signs will be posted to alert motorists to closures.

The sewer placement will proceed north towards Keystone Road, during which storm sewer will be tunneled through a narrow area between homes on the north side of Koepke Road.

While the sewer crew is installing this storm sewer, grading crews will return to begin the final grading and compaction of West Park, and distribution of topsoil.

Please check back weekly for project updates.

West Park storm sewer installation